Greenfield mobile launches in this region are usually constrained by three things: a licence with obligations attached, a spectrum grant with a defined start, and a commercial plan that assumed a launch date before anyone dimensioned the network. What separates launches that hold their date from launches that slip two quarters is almost entirely the order of the first six months.
Months 1–2: define, dimension, decide
Everything downstream depends on the numbers agreed here. Subscriber forecast by segment, traffic per subscriber, service mix, coverage obligation from the licence, and the spectrum actually granted. From those: core sizing, radio site count and configuration, transport topology, and a bill of materials specific enough to quote against.
Vendor selection belongs in this window too, and it should follow the design rather than precede it. Operators that select a vendor first and dimension afterwards buy the wrong configuration and discover it during acceptance.
The deliverable at the end of month two is a high-level and low-level design, a procurable bill of materials, and a migration and phasing plan. Not a slide deck.
Months 2–5: procure, and start voice
Procurement runs long in this region because lead times are real and customs is real. Order against the bill of materials early, consolidate regionally, and flag every long-lead item so the build sequence can be planned around it rather than interrupted by it.
In parallel — and this is the step most often deferred — start the voice workstream. IMS integration, device certification, interconnect and roaming testing all depend on third parties and consume calendar time that cannot be compressed by adding people. Starting voice in month two rather than month seven is the single highest-leverage scheduling decision in a greenfield build.
Also in this window: OSS and BSS selection and integration planning. Charging, policy and provisioning have to understand the services the commercial plan intends to sell. A network that works and cannot bill has not launched.
Months 4–8: build
Site acquisition, civil works, power, installation and commissioning, running as a rolling process rather than a phase. Core deployment on commodity hardware happens early in this window because everything else integrates into it.
Transport is built ahead of the radio it serves, not alongside it. Radio sites waiting on backhaul are the most common form of visible non-progress in a build programme.
Months 7–10: integrate and test
End-to-end integration across core, radio, transport, IMS and OSS/BSS. Interoperability testing across vendor boundaries. Drive testing. Load and device testing under representative conditions.
This is where multi-vendor programmes either converge or reveal that nobody owns the seams. If the contract did not name an integration owner with acceptance accountability, this is the month the operator discovers it has become the integrator.
Months 9–11: acceptance and friendly user
Acceptance against end-to-end KPIs, under load, at coverage boundaries, with the real device mix — and with defined remedies, not a list of open items. Then a friendly-user trial with real subscribers on real handsets, which is the only test that finds what the test plan did not imagine.
Month 12: launch, and the operating model
Commercial launch is an event; the operating model is the thing that has to exist before it. NOC, O&M, spares and repair, escalation paths, vendor management and service-level reporting should be running during the friendly-user period, not staffed after launch.
The three decisions that determine the date
Start voice in month two. Not month seven.
Name one integration owner with acceptance accountability. In the contract, before procurement.
Build transport ahead of radio. Not in parallel.
Programmes that make these three decisions launch within a quarter of their plan. Programmes that make none of them launch late, and the post-mortem always identifies the same three.